PeopleSoft PeopleTools Upgrade
Description
Referencing an Oracle Tech Update, the support for PeopleTools (PT) 8.55 ends in June 2019 and the PT 8.57 GA anticipated Dec 2018 for cloud and Jun 2019 for on premise.
As a result, CSU will be required to move to PT 8.56 before Jun 2019.
Status
Completed
Start and Delivery Dates
07/01/2018 to 04/15/2019
Department/Committee
Instructional and Information Technology Services, IITS - Enterprise Applications and Analytics
Status Update
04/15/2019: Upgrade was successful. Project Completed.
04/05/2019: The PeopleTools 8.56 is on schedule to go-Live weekend of 4/12/2019.
01/28/2019: The PeopleTools 8.56 is In Progress as of 1/7/2019. The changes include: branding and tools customization's, reconfigure SSO, and ldap authentication. Go-Live weekend is 4/12/2019.
07/11/2018: Dev Pass in Jan 2019; MTP April 2019
Strategic Alignment
Goal #1 – ENSURE AN ADAPTABLE AND SUSTAINABLE TECHNOLOGY ENVIRONMENT
1.1 CSUSM continuously improves, deploying new systems, services, and strategies that improve efficacy and efficiency